100 | 62 | Lot prep. Set Temp. Pole |
120 | 61 | Slab forms place barrel. Call for set back inspection |
121 | 60 | Fill dirt |
122 | 59 | Knock down dirt |
125 | 58 | Plumbing rough. Call for plumbing rough inspection |
128 | 57 | Plumbing rough inspection |
127 | 56 | Plumbing rough re-inspection |
128 | 55 | Re-grade, poly, Install ground and conduit. (Call for copper) |
130 | 54 | Grade, poly |
140 | 53 | Reinforcing, block out |
145 | 52 | pre-poly inspection |
150 | 51 | Pour foundation (Call cable) |
151 | 50 | Wreck forms. Paint address on foundation |
155 | 49 | Rough grade |
160 | 48 | Form driveway, patio |
165 | 47 | pre-pour inspection |
170 | 46 | Pour flatwork |
170 | 45 | wreck forms, place barricade |
209 | 44 | Deliver frame package |
210 | 43 | Frame start |
-- | -- | Frame |
-- | -- | Day two frame |
215 | 42 | cornice (Deliver Windows) |
225 | 41 | Start cornice, blocking, decking (call for dry-in) |
228 | 40 | Complete cornice, blocking, deliver roof / gable vents |
230 | 39 | Frame, cornice, dry-in complete, Deliver exterior doors |
235 | 38 | Start plumbing top out |
240 | 37 | Start A/C rough, set tubs |
245 | 36 | Start electric rough, install fireplace |
250 | 35 | Complete roughs, stock roof |
255 | 34 | Install overhead door, alarm pre-wire |
260 | 33 | Frame punch, stock sheetrock |
265 | 32 | Complete frame punch (Call frame inspection) |
270 | 31 | City and KB frame inspection |
271 | 30 | Complete inspection |
272 | 29 | inspect city, drain tubs (Call batt insulation) |
275 | 28 | Batt insulation (call insulation inspection) |
276 | 27 | Insulation inspection. Alert masonry |
278 | 26 | Install sheetrock |
-- | -- | Complete sheetrock (Call wallboard inspection) |
280 | 25 | Wallboard inspection |
281 | 24 | Tape |
281 | 23 | Tape / Float |
-- | -- | Day three tape / float |
285 | 22 | Finish float |
290 | 21 | Texture. Deliver interior doors, trim, cabinets, shutters |
300 | 20 | Set cabinets, start trim. Deliver door hardware packages |
308 | 19 | Complete Trim, Deliver electric fixtures |
310 | 18 | Latex, Measure tops |
-- | -- | Prep for paint |
318 | 17 | Enamel. 1st notice to whirlp--l |
|
319 | 16 | Start A/C Trim |
320 | 15 | Install vinyl/wood floor, tub/floor tile |
321 | 14 | Install tops |
-- | -- | Install tile / back splash |
325 | 13 | Start electric trim, deliver dishwasher, deliver atrium screen door |
330 | 12 | Plumbing trim, blow attic insulation |
340 | 11 | install mirrors, shower doors. Drywall make ready, |
345 | 10 | Install, install range / microwave / hood |
350 | 9 | Complete carpet, install screens |
360 | 8 | Make ready, install exterior door |
361 | 7 | Community team final scheduled |
362 | 6 | Complete community team punch |
363 | 5 | Touch up, clean |
364 | 4 | Final scheduled |
365 | 3 | Complete final |
366 | 2 | Final clean |
370 | 1 | Community team, Final, city and mortgage inspection cleared |
The final few days are for the buyerâs orientation and the walk-through punch items the homebuyer has listed. THIS IS AN IMPORTANT TIME FOR THE BUYER AND IS CRITIAL! AS THE BUYER, DO NOT SIGN OFF ON THE HOME UNTIL ALL ITEMS ARE DONE, EVEN IF THEY PROMISE TO DO THEM AFTER CLOSING.
|
371 | 0 | Buyer orientation |
372 | 0 | Work list |
373 | 0 | Work list |
374 | 0 | Work list |
380 | 0 | Install sod, buyer COE and move in |
385 | 0 | Sod installed |
This information is provided for potential homebuyers to allow them to see how fast this company works to build a home. Management has to construct homes this fast because the home office needs to push the numbers for the stockholders. In other words, itâs not about anything including quality but money. Read and you the future homebuyer can decide. If you donât believe it, ask a sales staff member how fast you can get in a home built that is not in inventory. |